The Submittals Module is used to track all Submittals for the project.
Quick Links
Use the links to quickly jump to the steps in the article below.
- Select Submittals from the Logs Menu and click on +New
Note:
This tutorial is for creating an original Submittal. To learn how to revise an existing Submittal, click here.
Note:
There are multiple ways to look at the Submittal information with the use of views. The views available are:
▪ *All Submittals
▪ *All Submittals by Status
▪ *Late Submittals
▪ *Open SubmittalsTo learn more about views, click here
- In the SUBMITTALS Section, enter the following information:
IMPORTANT:
Any field with an asterisk * is a required field and must be entered.
▪ Submittal Title: A descriptive title for the Submittal
▪ Submittal Status: A drop-down selection of the status for the Submittal
▪ Submittal Closed: Toggle indicates the original and possible revisions have now been resolved
▪ Ball-in-Court: The user who should be made aware of this item and is currently responsible for the item. When the record is saved an e-mail is sent to the Ball-in-Court. This will occur every time the Ball-in-Court is changed.
▪ Cc: Any additional users who should be aware of this item. When the record is saved an e-mail is sent to all listed in the Cc field. This will occur every time the Ball-in-Court is changed.Note:
▪ All BIC / Cc emails are tracked in the Email Notice Log.
▪ If there is no Ball-in-Court listed, users in the Cc column will not receive any notifications.
▪ If a user is added to the Cc column, only that user will be notified of their addition.
▪ If users are added as individuals and as a member of a group, they will only receive one notification email. - On the GENERAL INFORMATION Section, enter the following information:
▪ To: Select from the drop-down the person and company the Submittal is going to (This is populated from the Project Directory)
▪ From: Select from the drop-down the person and company the Submittal is coming from (This is populated from the Project Directory)
▪ Submittal Category: A drop-down selection of the appropriate category for the Submittal
▪ Spec Section: A drop-down selection of the appropriate spec section related to the Submittal
▪ Initiated By: The person initiating the Submittal (This will default to the user entering the Submittal but may be modified)
▪ Initiated Date: The date the Submittal was initiated (This will default to the current date but may be modified) - Use the DISCUSSION Section for any discussions during the process.
▪ Discussion: Enter any discussion items here. Each entry will be date and time stamped and show the user who entered the discussion information
- Use the REVIEW Section to respond to the Submittal
▪ Response: The response to the Submittal
▪ Responded By: The user who responded to the Submittal
▪ Responded Date: The date the Submittal was reviewed - Use the REVISIONS Section to create a new revision of the Submittal
Note:
Learn more on creating a revision here
▪ Create Revision?: When a person is ready to resubmit a Submittal item, they will go to the original Submittal and check this box
▪ New Revision Number: Enter the revision number for the Submittal revision being created from this submittal - Use the ATTACHMENTS Section to add or view any attachments for the Submittal
Note:
To learn how to attach files, click here
IMPORTANT:
When finished entering information, click Save and Continue or Save and Close